SAP C-TS412-1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 22
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Controlling area
- B. Sales organization
- C. Operating concern
- D. Company code
- E. Plant
Answer: A,D,E
NEW QUESTION 23
What is the reason for assigning billing plans in customer projects?
- A. Billing plans are copied automatically to the sales order item.
- B. Billing plans are prerequisites for quotation creation.
- C. Billing plans enable the billing process to be carried out.
- D. Billing plans are used for revenue planning.
Answer: C
NEW QUESTION 24
To which object can you assign a factory calendar?
- A. Relationship
- B. Network header
- C. Material component
- D. Milestone
Answer: B
NEW QUESTION 25
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Preliminary purchase requisition for WBS element
- B. Planned order
- C. Third-party order
- D. Reservation for WBS element
- E. Purchase requisition and Reservation for WBS element
Answer: A,D,E
NEW QUESTION 26
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Sales order items
- B. Project definition
- C. WBS elements
- D. Milestones
Answer: A,C
NEW QUESTION 27
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
- A. Purchase order items
- B. Sales order items
- C. Internal orders
- D. Reservations
Answer: A,D
NEW QUESTION 28
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Results analysis key
- B. Investment profile
- C. Costing sheet
- D. Settlement rule
Answer: C
NEW QUESTION 29
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Requirement class
- B. Control key
- C. Item category
- D. Project profile
Answer: A
NEW QUESTION 30
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The availability check for material components indicates missing parts.
- B. The material is assigned to the activity as a non-stock material.
- C. The material master is set to external procurement.
- D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
Answer: A,D
NEW QUESTION 31
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing budget for material components
- D. Missing reservations for material components
Answer: B
NEW QUESTION 32
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Sales order
- B. Billing
- C. Inquiry
- D. Quotation
Answer: A,D
NEW QUESTION 33
How can you grant individual authorization for WBS elements and networks?
- A. Define a user status to lock the business transaction Update Project.
- B. Activate access control lists (ACL) for the user master record.
- C. Set the system status to "Lock Master Data".
- D. Activate access control lists (ACL) for the project profile and the network profile.
Answer: D
NEW QUESTION 34
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Project-relevant purchase orders
- B. Capacity requirements
- C. Production orders assigned to WBS elements
- D. Maintenance orders assigned to an activity
Answer: B,D
NEW QUESTION 35
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.
- A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
- B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
- C. You can only maintain the actual start of a WBS element if the finish date is not maintained.
- D. You can always maintain the actual start and finish date of a WBS element.
Answer: A,B
NEW QUESTION 36
What functionality can you perform with activity elements?
- A. Assign work centers and capacities
- B. Create relationships
- C. Assign material
- D. Schedule WBS elements
Answer: B
NEW QUESTION 37
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the reduction strategy is set in the network header
- B. If the reduction strategy is set in each activity
- C. If the appropriate reduction type is set in the parameters for network scheduling
- D. If the maximum reduction level is less than 100
Answer: A,C
NEW QUESTION 38
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements type
- B. Schedule line category
- C. Requirements class
- D. Item category
Answer: D
NEW QUESTION 39
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Free planning
- C. Strict bottom-up
- D. Bottom-up
Answer: D
NEW QUESTION 40
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Trigger automatic capacity leveling inside the project planning board.
- B. Maintain subordinate internal activity elements assigned to other work centers.
- C. Increase the capacities of the work center in the project planning board.
- D. Shift activities backward or forward on the time axis where more capacities are available.
Answer: A,D
NEW QUESTION 41
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Results analysis
- B. Settlement
- C. Confirmations
- D. Progress analysis
- E. Milestone trend analysis
Answer: A,B,D
NEW QUESTION 42
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching via status selection profile
- B. By searching for the individual status
- C. By searching for the status profile
- D. By searching via status combination code
Answer: B,C
NEW QUESTION 43
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
- B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
- D. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt
Answer: A
NEW QUESTION 44
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. Material components can be assigned to activity elements.
- B. A network can be activity-account-assigned and header-account-assigned.
- C. Relationships can be used to connect activities of different networks.
- D. A network activity can be assigned to several WBS elements.
Answer: B,C
NEW QUESTION 45
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
- A. Basic dates
- B. Forecast dates
- C. Baseline dates
- D. Planned dates
Answer: A,B
NEW QUESTION 46
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. Material determination is mandatory.
- B. DIP is used to create a quotation.
- C. Sales prices are maintained in the DIP profile.
- D. Sources can be based on line items.
- E. Usage of cost elements is mandatory.
Answer: B,C,D
NEW QUESTION 47
......