NEW QUESTION 46
A bond that guarantees the bidder will enter into a contract on the basis of his/her bid is referred to as:
- A. Liability bond
- B. Surety bond
- C. Performance bond
- D. Bid bond
Answer: D
NEW QUESTION 47 
The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
In the A relationship, the subcontractor might use an unbalance bid to:
- A. Decrease the chances of extended claim litigation
- B. To get more payment early in the job
- C. Reduce the risk of quantities being greater than estimated
- D. Provides an alternative to competitive bidding
Answer: C
NEW QUESTION 48
A work breakdown structure (WBS) is developed because:
- A. It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans
- B. It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence
- C. It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup
- D. It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.
Answer: A
NEW QUESTION 49 
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?
- A. 16,215
- B. 14,201
- C. 12,000
- D. 10,526
Answer: D
NEW QUESTION 50
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?
- A. Ratio/level of effort
- B. Units completed
- C. Start/finish
- D. Incremental milestone
Answer: D
NEW QUESTION 51
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Fred Fiedler's contingency model suggests that:
- A. A relationship oriented leader described the least preferred worker in an unfavorable light
- B. Successful leadership depends upon a good match
- C. Successful leadership can always be imposed by experienced supervision
- D. Leadership styles are just the opposite of the managerial grid model
- E. between the style of the leader and the demands of the situation
Answer: E
NEW QUESTION 52
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return?
- A. 10.4%
- B. 9.1%
- C. 9.9%
- D. 8.3%
Answer: B
NEW QUESTION 53
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:
- A. To fall within the percentage range stated
- B. To be higher or lower that the percentages stated
- C. To be outside the percentages stated
- D. To be exactly the percentages stated
Answer: A
NEW QUESTION 54
____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.
- A. Scheduling
- B. Forecasting
- C. Planning
- D. Modeling
Answer: A
NEW QUESTION 55
____________is defined as the earned work hours or dollars for all accounts divided by the budgeted work hours or dollars for all accounts.
- A. Percent complete
- B. Forecast
- C. Earned value
- D. Cost to complete
Answer: A
NEW QUESTION 56
When a person hears the words being said to him/her, but does not receive the message of the words, it is called
- A. Passive listening
- B. Directive listening
- C. Reflective listening
- D. Judgmental listening
Answer: A
NEW QUESTION 57
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?
- A. Class 5 - order of magnitude estimate with +50% / -30% accuracy
- B. Class 1 - order of magnitude with +30% / -30% accuracy
- C. Class 2 - definitive estimate with +15%/-5% accuracy
- D. Class 4 - budget estimate with +30% / -15% accuracy
Answer: A
NEW QUESTION 58
Some of the principles of good communication are:
- A. Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated
- B. Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda
- C. The social process by which people in a specific situation construct meaning using symbolic behavior
- D. Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message
Answer: A
NEW QUESTION 59
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following interest rates disregards the effects of compounding periods that occur more frequent than annually?
- A. Simple interest rate
- B. Nominal interest rate
- C. Continuous compounding rate
- D. Minimum attractive rate of return
Answer: B
NEW QUESTION 60
Which of the following is NOT a type of float?
- A. Free
- B. Open end
- C. Negative
- D. Total
Answer: B
NEW QUESTION 61 
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the range of estimated quantities?
- A. $26.78 to $75.00
- B. $48.22
- C. $45 to $530
- D. $485
Answer: C
NEW QUESTION 62
What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.
- A. Alternate
- B. Engineer
- C. Project Manager
- D. Agent
Answer: D
NEW QUESTION 63 
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
6,573 hours have been expended to date. Planned completion at this time is 60%. The project is determined to be 55% complete. How many hours have been earned?
- A. 7,200
- B. 6,573
- C. 6,960
- D. 6,600
Answer: B
NEW QUESTION 64
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
When analyzing a precedence diagram schedule, the "backward pass"
- A. Allows activities to finish as soon as all their 'predecessor' relationships are satisfied
- B. Calculates the earliest allowable start and finish times for the activities in the schedule
- C. Determines the duration of each activity
- D. Allows total float to be calculated
Answer: B
NEW QUESTION 65
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Annual estimated tax would be:
- A. $10,500
- B. $11,925
- C. $3,869
- D. $5,565
Answer: D
NEW QUESTION 66
An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.
Answer the question using a straight line depreciation and a 10% interest rate.
Which of the following should be included in the life-cycle cost analysis of a power plant?
- A. Capacity factor, end product units, physical dimensions
- B. Factory expenses, distribution expenses, mark-up
- C. Construction cost, operating cost, maintenance cost
- D. Resources, work activities, final cost objects
Answer: C
NEW QUESTION 67 
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the relative frequency of unit costs from Atlanta, GA?
- A. $40.59
- B. $48.33
- C. 33.33%
- D. 0
Answer: C
NEW QUESTION 68
A contract clause that provides the owner with the right to terminate the contract irrespective of the general contractor's liability is:
- A. Termination of contract - default
- B. Breach of contract
- C. Termination of contract - convenience
- D. Substantial completion
Answer: C
NEW QUESTION 69
......
Authentic Best resources for CCP Online Practice Exam: https://www.examtorrent.com/CCP-valid-vce-dumps.html
Get the superior quality CCP Dumps with explanations waiting just for you, get it now: https://drive.google.com/open?id=1K-EP97YSBNNrzKLDrdIdqLxYxSKd7JU7