NEW QUESTION # 27
You are carrying out an audit to ISO 9001 at an organisation which offers regulatory consultancy services to manufacturers of cosmetics.
You are interviewing the Technical Director (TD), who manages a team of regulatory experts responsible for providing regulatory services to customers.
You: "How do you ensure your regulatory team's competence concerning regulatory requirements is maintained?" TD: "The two Regulatory Experts we employ full-time have years of experience of working in the cosmetics industry." You: "How is their regulatory competence maintained?" TD: "They are dedicated individuals with lots of contacts in the sector." You: "How does the business enable them to maintain their understanding of current regulatory requirements?" TD: "We leave that up to them."
Answer:
Explanation:
Explanation:
A screenshot of a computer Description automatically generated
NEW QUESTION # 28
Which two of the following aspects of a quality management system must the organisation continually improve?
- A. Efficiency
- B. Suitability
- C. Adaptability
- D. Responsiveness
- E. Applicability
- F. Effectiveness
Answer: A,F
Explanation:
According to the ISO 9001:2015 document, the organisation must continually improve the suitability, adequacy, and effectiveness of the quality management system1. However, among the six options given, only effectiveness is directly mentioned as an aspect of the quality management system that must be continually improved. Therefore, C is one of the correct answers.
Efficiency, on the other hand, is not explicitly stated as an aspect of the quality management system that must be continually improved, but it is implied by the quality management principle of improvement, which states that successful organisations have an ongoing focus on improvement2. One of the key benefits of applying this principle is improving operational effectiveness and efficiency2. Therefore, E is another correct answer.
Suitability, adaptability, responsiveness, and applicability are not aspects of the quality management system that must be continually improved, according to the ISO 9001:2015 document. They may be related to the quality management system, but they are not the focus of continual improvement.
Therefore, the correct answer is C and E.
References: 1: ISO 9001:2015 - Quality management systems - Requirements 2: ISO - Quality management principles
NEW QUESTION # 29
Which of the following two documents does an auditor need to prepare and complete prior to the on-site audit?
- A. Findings
- B. Risk Matrices
- C. Audit Report
- D. Audit Plan
- E. Procedures
- F. Checklist / Prompts
Answer: D,F
Explanation:
According to ISO 19011:2018, clause 6.3, the audit plan is a document that provides the basis for agreement regarding the conduct of the audit. The audit plan should include the information listed in my previous response, such as the audit objectives, scope, criteria, schedule, team, methods, report, etc. The audit plan should be prepared and completed prior to the on-site audit, and should be communicated to the audit team and the auditee1.
According to ISO 19011:2018, clause 6.4.3, the checklist / prompts are documents that list the questions or topics that need to be covered during an audit. The checklist / prompts can help the auditor to collect and verify information relevant to the audit criteria, and to ensure the consistency and completeness of the audit.
The checklist / prompts should be prepared and completed prior to the on-site audit, and should be based on the audit plan and the audit scope and objectives1.
Therefore, the two documents that an auditor needs to prepare and complete prior to the on-site audit are B and D, as they are essential for planning and conducting the audit. The other options are not correct, as they are either prepared or completed after the on-site audit, or not required by the standard:
*A. Audit Report: The audit report is a document that provides a complete, accurate, concise, and clear record of the audit. The audit report should include the information listed in my previous response, such as the audit objectives, scope, criteria, findings, conclusions, etc. The audit report should be prepared and completed after the on-site audit, and should be distributed to the audit client and the auditee1.
*C. Procedures: Procedures are documents that specify the way activities are to be performed. Procedures may be part of the audit criteria, if they are part of the organization's management system, or part of the audit programme, if they are part of the certification body's or registrar's requirements. Procedures are not prepared or completed by the auditor prior to the on-site audit, but rather reviewed or followed by the auditor during the audit1.
*E. Risk Matrices: Risk matrices are tools that help to assess and prioritize the risks and opportunities associated with the audit programme or the audit. Risk matrices may be part of the audit programme management, if they are used to determine and evaluate the audit programme risks and opportunities, or part of the audit preparation, if they are used to determine and evaluate the audit risks and opportunities. Risk matrices are not prepared or completed by the auditor prior to the on-site audit, but rather used or updated by the auditor during the audit programme management or the audit preparation1.
*F. Findings: Findings are the results of the evaluation of the collected audit evidence against the audit criteria.
Findings can indicate either conformity or nonconformity, as well as positive aspects or opportunities for improvement. Findings are not prepared or completed by the auditor prior to the on-site audit, but rather generated and recorded by the auditor during the audit activities1.
References: ISO 19011:2018(en), Guidelines for auditing management systems
NEW QUESTION # 30
In the context of a third-party audit, select the issue which is not expected to be included in the audit plan.
- A. Number of sites to be audited
- B. Risk to achieving audit objectives
- C. Scope of the audit
- D. Expectations of the organisation's management
Answer: D
Explanation:
According to ISO 19011:2018, clause 6.3.2, the audit plan is a document that provides the basis for agreement regarding the conduct of the audit. The audit plan should include the following information1:
*the audit objectives, scope and criteria
*the audit team members and their roles and responsibilities
*the audit schedule, including the date, time and location of each audit activity
*the expected time and duration of meetings and interviews
*the allocation of appropriate resources to critical areas of the audit
*the identification of the audit client and the auditee
*the identification of the guides and observers, if any
*the documents and records to be reviewed before and during the audit
*the audit methods and tools to be used
*the audit language and terminology
*the audit report content, format, distribution and expected completion date
*the risk to achieving audit objectives and the contingency plan, if any Therefore, the issue which is not expected to be included in the audit plan is C, expectations of the organisation's management. This issue is not relevant to the conduct of the audit, as the audit is based on the audit criteria, not on the management's expectations. The management's expectations may be considered during the audit initiation or the audit programme management, but they are not part of the audit plan.
References: ISO 19011:2018(en), Guidelines for auditing management systems, How to create an ISO 9001 internal audit plan - Advisera
NEW QUESTION # 31
Which two of the following are the key expected results of a quality management system that conforms to the requirements of ISO 9001:2015?
- A. Consistently provide products that meet customers' requirements
- B. Increased profits
- C. Enhanced customer satisfaction
- D. Decreased number of nonconforming products in all stages of the manufacturing cycle
- E. Decreased number of warranty claims
- F. Decreased number of management system nonconformities
Answer: A,C
Explanation:
According to the ISO 9001:2015 document, the key expected results of a quality management system that conforms to the requirements of ISO 9001:2015 are:
*the ability to consistently provide products and services that meet customer and applicable statutory and regulatory requirements;
*the enhancement of customer satisfaction.
These results are derived from the quality management principles of customer focus and process approach, which are the basis of the ISO 9000 family of standards1. Customer focus means understanding and meeting customer needs and expectations, as well as exceeding them when possible1. Process approach means managing activities as interrelated processes that function as a coherent system, which leads to consistent and predictable results1.
Therefore, the correct answer is C and F.
References: 2: ISO 9001:2015 - Quality management systems - Requirements 1: ISO - Quality management principles
NEW QUESTION # 32
You are an auditor from a construction organisation who is conducting a second party audit to ISO 9001 at a steel rolling mill producing structural steelwork. When auditing the rolling process, you find that the operator who is unloading the furnace does not use the adjacent infrared pyrometer to measure the appropriate product temperature in readiness for the next production stage.
You: "How do you tell when the billet is ready for the rolling stage?"
Operator: "I've done this job for 20 years. I can tell by the bright red colour." You: "What happens if the colour is wrong?" Operator: "The billet goes back into the furnace." You: "Is the pyrometer ever used?" Operator: "Only in borderline cases." You continue to interview the operator and find that around 25% of the billets are sent back to the furnace.
This includes 80% of the borderline cases.
Select three options that would provide evidence of conformance with clause 9.1.1 of ISO 9001.
- A. An increase in the use of the pyrometer by operators.
- B. Annual review records for furnace operators.
- C. Certification of conformance to national standards from the manufacture of the pyrometer.
- D. A quality objective to achieve lower recycle rates for billets.
- E. Planning for monitoring and measuring the billet temperature.
- F. A procedure that provides instruction in taking billet temperature.
- G. Maintenance plan for the furnace.
- H. Periodic analysis of the results of temperature checks.
Answer: E,F,H
Explanation:
According to ISO 9001:2015, clause 9.1.1, the organization is required to determine what needs to be monitored and measured, the methods for monitoring, measurement, analysis and evaluation, as applicable, to ensure valid results, and when the monitoring and measuring shall be performed. The organization is also required to retain appropriate documented information as evidence of the results.
Therefore, in the scenario given, the organization should have planned for monitoring and measuring the billet temperature, as it is a critical factor for the quality of the product and the process. The organization should also have established a procedure that provides instruction in taking billet temperature, using the pyrometer or other suitable methods, to ensure consistency and accuracy. The organization should also have performed periodic analysis of the results of temperature checks, to identify trends, problems, and opportunities for improvement.
Hence, the options that would provide evidence of conformance with clause 9.1.1 of ISO 9001 are A, E, and F, as they are aligned with the requirements of the clause. The other options are either irrelevant or not directly related to clause 9.1.1, as they do not pertain to the monitoring and measurement of the billet temperature.
References:
ISO 9001:2015(en), Quality management systems - Requirements, clause 9.1.1 ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.4.4 and 6.7.2 ISO 9001 Lead Auditor Training Course | IRCA Certified | BSI, section "Learning objectives" ISO 9001 Lead Auditor Course Material | 3FOLD Education Centre, module 5 and 6
NEW QUESTION # 33
You are carrying out an annual audit at an organisation that offers home security services. You are interviewing the Quality Manager (QM) You: "Would you tell me about your management review process?" QM: "The senior management team plans to review the management system every six months. The review follows a set agenda and records are maintained." You: "May I see the records from the last two management reviews?" Narrative: The Quality Manager gives you the latest record, which shows the last management review took place nine months ago.
The Quality Manager then gives you the previous management review record, which took place one year before the latest review.
You: "Are there any other review reports in the last two years?
QM: "No, these are the only ones."
Answer:
Explanation:
Explanation:
Nonconformity report
ISO 9001 Clause Number: 9.3.1 Nature of problem: Management review has not been conducted at the defined frequency. ISO 9001 requirement that has not been fulfilled: ISO 9001 - "Top management shall review the organization's quality management system at planned intervals." Evidence: The last management review took place nine months ago, and the previous one took place one year before the latest review. The planned interval is six months.
NEW QUESTION # 34
You have been nominated audit team leader of a third-party audit. Which of the following could be the two most relevant objectives of this audit?
- A. Evaluate the satisfaction interested parties
- B. Evaluate the benefits obtained since the implementation of the management system
- C. Identify opportunities for improvement
- D. Evaluate the capability of the management system to establish and achieve objectives
- E. Evaluate the effectiveness of the management system
- F. Identify the need of resources
Answer: D,E
Explanation:
Evaluate the effectiveness of the management system: This objective involves verifying that the quality management system meets the requirements of a specific standard, such as ISO 9001:2015, and that it achieves the intended results and outcomes. The audit team will collect and analyse audit evidence to determine the degree of conformity and performance of the quality management system23.
*Evaluate the capability of the management system to establish and achieve objectives: This objective involves verifying that the quality management system supports the strategic direction and policies of the organization, and that it addresses the needs and expectations of the interested parties. The audit team will assess the suitability, adequacy, and alignment of the quality management system objectives, and the effectiveness of the planning and implementation processes to achieve them23.
The other options are not the most relevant objectives of a third-party audit, according to the web search results from my internal tool. They may be related to other aspects or types of audits, but they are not the focus of a third-party audit.
Therefore, the correct answer is B and D.
References: 1: Safeguarding Your Business: The Power of Third-Party Security Audits 2: ISO 19011:2018 - Guidelines for auditing management systems 3: Third Party Audit - QMSGurus.com
NEW QUESTION # 35
Select six of the activities that are specifically required by ISO 17021-1 as part third-party (Certification Body) surveillance audit processes.
- A. Conduct a minimum number of annual surveillance audits during the certification period.
- B. Handling of customer complaints since last visit.
- C. Failing to meet financial responsibilities.
- D. Verify legal compliance.
- E. Review the calibration status of the instrumentation.
- F. Confirm effectiveness of internal audit and management review.
- G. Audit use of certification marks on marketing materials.
- H. Review the status of previously raised findings and audit effectiveness of any outstanding findings.
- I. Complete a full document review of the quality management system.
- J. Review changes to the QMS since last visit.
Answer: B,D,F,G,H,J
Explanation:
The activities that are specifically required by ISO 17021-1 as part of third-party (Certification Body) surveillance audit processes are:
*Option A: Audit use of certification marks on marketing materials. This option is correct because ISO
17021-1:2015 clause 9.6.2.2 requires the certification body to audit the client's use of marks and/or any other reference to certification, as applicable, to ensure conformity with the certification requirements.
*Option B: Review changes to the QMS since last visit. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review any changes affecting the client's quality management system and its ability to continue to fulfil the requirements of the standard used for certification.
*Option C: Confirm effectiveness of internal audit and management review. This option is correct because ISO
17021-1:2015 clause 9.6.2.2 requires the certification body to confirm the continuing effectiveness of the client's quality management system, including the effectiveness of the internal audit and management review processes.
*Option F: Review the status of previously raised findings and audit effectiveness of any outstanding findings.
This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review the status of findings and any corrective actions taken by the client in response to previous audits, and to verify the effectiveness of the implemented corrective actions.
*Option H: Verify legal compliance. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to verify the client's compliance with applicable statutory and regulatory requirements related to the scope of certification.
*Option I: Handling of customer complaints since last visit. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review the client's handling of customer complaints related to the certified activities since the last audit.
The following options are not correct:
*Option D: Complete a full document review of the quality management system. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to complete a full document review of the quality management system during surveillance audits. A full document review is only required during the initial certification audit or when there are significant changes to the quality management system or the certification requirements.
*Option E: Failing to meet financial responsibilities. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to audit the client's financial responsibilities during surveillance audits. The certification body may have contractual arrangements with the client regarding the payment of fees, but this is not part of the surveillance audit process.
*Option G: Review the calibration status of the instrumentation. This option is not correct because ISO
17021-1:2015 clause 9.6.2.2 does not require the certification body to review the calibration status of the instrumentation during surveillance audits. The certification body may audit the client's monitoring and measuring resources as part of the quality management system requirements, but this is not a specific activity required by ISO 17021-1.
*Option J: Conduct a minimum number of annual surveillance audits during the certification period. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to conduct a minimum number of annual surveillance audits during the certification period. The certification body may determine the frequency and duration of surveillance audits based on the risk and performance of the client, but this is not a specific activity required by ISO 17021-1.
References:
*ISO 17021-1:2015 Conformity assessment - Requirements for bodies providing audit and certification of management systems - Part 1: Requirements
*ISO 9001 Lead Auditor Course Material, Module 7: Audit Follow-up and Surveillance, Slide 8: Surveillance Audit
*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 7.2: Audit Follow-up and Surveillance
*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection
3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies
NEW QUESTION # 36
Select the term that best describes the purpose of retaining documented information in a quality management system to ISO 9001.
- A. To facilitate auditing for proof of conformity to the standard.
- B. To safeguard the integrity of the quality management system.
- C. To provide confidence in the effectiveness of the quality management system.
- D. To support the operation of the processes of the quality management system.
Answer: D
Explanation:
Documented information is a means by which an organization demonstrates compliance. It communicates what we do and how we do things, it communicates what happened and what results were achieved. It is, essentially, a tool for communication. ISO 9001:2015 allows an organization flexibility in the way it chooses to document its quality management system (QMS). This enables each individual organization to determine the correct amount of documented information needed in order to demonstrate the effective planning, operation and control of its processes and the implementation and continual improvement of the effectiveness of its QMS. The standard states that the organization shall maintain documented information to the extent necessary to support the operation of processes and retain documented information to the extent necessary to have confidence that the processes are being carried out as planned. Therefore, the purpose of retaining documented information is to support the operation of the processes of the QMS, not to facilitate auditing, provide confidence or safeguard integrity, which are secondary benefits of documented information.
References: Guidance on the requirements for Documented Information of ISO 9001:2015, ISO 9001:2015 documented information | CQI | IRCA, Documented Information Required by ISO 9001:2015 - 9000 Store
NEW QUESTION # 37
The following are stages of an audit, put them in the order they would be conducted.
Answer:
Explanation:
Explanation:
Establishing the audit programme objectives
Determining and evaluating the audit programme risks and opportunities
Establishing the audit programme
Initiating the audit
Preparing all audit activity
Conducting the audit activities
According to ISO 19011:2018, clause 5, the audit programme is a set of one or more audits planned for a specific time frame and directed towards a specific purpose. The audit programme includes all activities necessary to plan, organize, and conduct the audits. The audit programme management involves the following steps1:
Establishing the audit programme objectives: The audit programme objectives define the intended outcomes of the audit programme, such as verifying conformity, evaluating performance, identifying improvement opportunities, etc. The audit programme objectives should be aligned with the strategic direction and policies of the organization and the needs and expectations of the interested parties.
Determining and evaluating the audit programme risks and opportunities: The audit programme risks and opportunities are the factors that can affect the achievement of the audit programme objectives, such as changes in the internal or external context, availability of resources, competence of auditors, etc. The audit programme risks and opportunities should be identified, analyzed, and evaluated to determine the appropriate actions to address them.
Establishing the audit programme: The audit programme is established by defining the audit programme scope, criteria, methods, and resources. The audit programme scope defines the extent and boundaries of the audit programme, such as the processes, functions, sites, activities, etc. that will be audited. The audit programme criteria are the set of policies, procedures, or requirements used as a reference for the audits. The audit programme methods are the techniques used to conduct the audits, such as interviews, observations, document review, sampling, etc. The audit programme resources are the human, technical, and financial resources needed to implement the audit programme.
Initiating the audit: The audit initiation is the process of formally establishing the arrangements for an individual audit within the audit programme. The audit initiation involves contacting the auditee and the audit client, confirming the audit objectives, scope, and criteria, and obtaining the necessary information and access for the audit.
Preparing all audit activity: The audit preparation is the process of developing the audit plan and the audit work documents for an individual audit. The audit plan is a document that provides the basis for agreement regarding the conduct of the audit, such as the audit schedule, the audit team, the audit methods, the audit language, the audit report, etc. The audit work documents are the records that provide evidence of the audit activities, such as the audit checklist, the audit notes, the audit findings, etc.
Conducting the audit activities: The audit activities are the processes of collecting and verifying audit evidence and evaluating it against the audit criteria to make the audit conclusions. The audit activities include the opening meeting, the communication during the audit, the roles and responsibilities of the audit team and the auditee, the audit evidence collection and verification, the audit findings generation and recording, the closing meeting, and the audit report preparation and distribution.
References: ISO 19011:2018(en), Guidelines for auditing management systems
NEW QUESTION # 38
You work as an external quality consultant for an organisation, 'A', which provides packaged food to the public. You are asked to lead a team (you as the leader and two other auditors) to audit a supplier, 'B', to ISO
9001 which provides packaging materials to your organisation. It is 4 pm and the audit is close to an end; you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting. The Closing meeting was scheduled at 5 pm.
You, as Audit Team Leader, audited top management. You explain to the audit team that you identified two nonconformities:
a. There is no documented information on Top Management Reviews, as required in clause 9.3 of ISO
9001:2015.
b. There is no evidence of Top Management Commitment as required in clause 5.1 of ISO 9001:2015. (e.g., not ensuring the availability of resources to operate the QMS, not ensuring the establishment of objectives, no promotion of improvement, no promotion of the process approach).
All agreed to present these two nonconformities. They went to meet the Top Management of 'B' and noticed that the General Manager and three other managers (Production, Human Resources, and Sales) were present in the meeting room.
Considering the seriousness of the two nonconformities to Top Management, as audit team leader, from the following select the best option:
- A. Present the nonconformities to the whole group and inform that you will recommend your company to remove them from the approved suppliers list.
- B. Present the nonconformities to the whole group and analyse with them how to overcome this situation.
- C. Ask the General Manager to have a private conversation in which you present the nonconformities only to him because of their sensitive nature.
- D. Present the nonconformities to the managers, inform them that the report will be sent within 10 days, close the meeting and leave the site.
Answer: B
Explanation:
According to the guidance on conducting the audit closing meeting1, the audit team leader should provide a summary of the audit findings and conclusions, invite discussions, and agree on timelines for any corrective actions. The audit team leader should also be respectful, constructive, and objective when presenting the nonconformities, and avoid any personal or emotional comments. The audit team leader should also consider the impact of the disruptive event (such as the Covid-19 pandemic) on the auditee's context, interested parties, and risks2, and acknowledge any good practices or improvements observed during the audit. Therefore, option D is the best option, as it follows the best practices for the closing meeting and allows the auditee to understand the nonconformities and their implications, and to participate in the analysis and resolution of the issues. Option A is not correct, as it is not respectful, constructive, or objective, and it does not invite any discussion or feedback from the auditee. It also assumes that the audit team leader has the authority to recommend the removal of the supplier from the approved list, which may not be the case. Option B is not correct, as it does not provide enough information or explanation to the auditee, and it does not allow any discussion or feedback from the auditee. It also does not follow the best practices for the closing meeting, such as providing a summary of the audit, acknowledging any good practices, and agreeing on timelines for corrective actions. Option C is not correct, as it does not involve the other managers who are responsible for the functions or processes that were audited, and who may have valuable input or information to share. It also does not follow the best practices for the closing meeting, such as providing a summary of the audit, inviting discussions, and agreeing on timelines for corrective actions. References: 1: Conducting the Audit Closing Meeting: Sharing the Results2: Auditing ISO 9001:2015 in the Context of a Disruptive Event.
NEW QUESTION # 39
Match the process descriptions below to the process names:
Answer:
Explanation:
Explanation:
A white background with black text Description automatically generated
NEW QUESTION # 40
During a second-party audit of a dairy farm (by a potential customer) complying with ISO 9001:2015, the auditor verifies that there is large variability in the daily production of the milking yard. The current agreement with their only customer is to provide 2,000 litres per day. However, in the last two years, they have noticed an increasing variability in daily production.
If they produce less than 2,000 litres, they are penalised with a fine of 1.5 pesos for every litre that they do not provide. If they produce more than 2,000 litres, they use the extra milk to feed the pigs.
This process has been in operation for decades. The dairy farm was founded by the grandfather of the current owners, who did not want to alter the established practices.
The auditor raises a nonconformity on the basis that the process is not under control (Clause 8.1).
If you had been the auditor, which one of the following actions would you have accepted?
- A. Analyse the daily dispatch of milk for 7 days to determine its variability.
- B. Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer.
- C. Retain the current contract and try to sell the occasional surplus milk to a second customer.
- D. Apply the existing process of addressing the risks and opportunities of milk production.
Answer: D
Explanation:
The action that the auditor would have accepted is:
*Option B: Apply the existing process of addressing the risks and opportunities of milk production. This option is correct because ISO 9001:2015 clause 8.1 requires the organization to plan, implement and control the processes needed to meet the requirements for the provision of products and services, and to implement actions determined in clause 6.1, which refers to the actions to address risks and opportunities. The organization should apply the existing process of addressing the risks and opportunities of milk production, which may include identifying the sources of variability, assessing the potential impacts and consequences, determining and implementing appropriate actions to reduce or eliminate the variability, monitoring and measuring the effectiveness of the actions, and reviewing and updating the actions as necessary.
The following options are not correct:
*Option A: Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.
*Option C: Retain the current contract and try to sell the occasional surplus milk to a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.
*Option D: Analyse the daily dispatch of milk for 7 days to determine its variability. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to implement actions to address risks and opportunities, as required by ISO 9001:2015 clause 8.1.
References:
*ISO 9001:2015 Quality management systems - Requirements, Clause 8: Operation, Subclause 8.1:
Operational planning and control, Subclause 8.2: Requirements for products and services
*ISO 9001 Lead Auditor Course Material, Module 4: ISO 9001:2015 Requirements, Slide 23: Clause 8 - Operation
*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 4.2: ISO 9001:2015 Requirements, Subsection 4.2.8: Clause 8 - Operation
*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection
3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies
NEW QUESTION # 41
According to ISO 19011, what two activities take place during the conduct of a audit follow-up?
- A. Verify corrections taken to fix the reported non-conformities
- B. Assign roles and responsibilities of observers
- C. Plan the next audit
- D. Verify legal compliance
- E. Verify the effectiveness of the implemented corrective actions
- F. Determine feasibility of the audit
Answer: A,E
Explanation:
According to ISO 19011:2018, clause 6.7, the audit follow-up is the process of verifying the completion and effectiveness of corrective actions taken by the auditee as a result of an audit. The audit follow-up can include two main activities:
Verifying the effectiveness of the implemented corrective actions: this means checking whether the actions taken by the auditee have addressed the root causes of the nonconformities and prevented their recurrence or occurrence in other areas. The verification can be done by reviewing documents, records, data, or other evidence provided by the auditee, or by conducting a follow-up audit on site or remotely.
Verifying corrections taken to fix the reported non-conformities: this means checking whether the auditee has corrected the nonconformities identified during the audit and eliminated their immediate effects. The verification can be done by reviewing documents, records, data, or other evidence provided by the auditee, or by conducting a follow-up audit on site or remotely.
The audit follow-up can be conducted as a separate audit or as part of a subsequent audit, depending on the audit programme, the audit objectives, the audit criteria, the audit scope, the audit risks, and the audit findings.
The audit follow-up should be planned and conducted in accordance with the same principles and processes as the initial audit, and the results should be documented and reported accordingly. References:
ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.7 ISO 19011 Management Systems Audit Checklist | Process Street, task 6.7.1 and 6.7.2 Conducting the Audit Follow-Up: When to Verify - The Auditor, section "Conducting the audit follow-up"
NEW QUESTION # 42
Match the process descriptions below to the process names:
Answer:
Explanation:
Explanation:
Match the process descriptions below to the process names:
The process by which the accuracy of test equipment is checked against a known standard. = Calibration The process by which a product or service is visually examined to determine conformity to requirements. = Evaluation The process by which data is examined in detail to reach a specific answer or answers. = Analysis The process by which a parameter of a product or service is examined to determine a specific value. = Measurement According to the ISO 9000:2015 - Quality management systems - Fundamentals and vocabulary, the definitions of the process names are as follows:
Calibration: operation that, under specified conditions, in a first step, establishes a relation between the quantity values with measurement uncertainties provided by measurement standards and corresponding indications with associated measurement uncertainties and, in a second step, uses this information to establish a relation for obtaining a measurement result from an indication.
Evaluation: determination of the suitability, adequacy or effectiveness of an object to achieve established objectives.
Analysis: detailed examination of the elements or structure of something.
Measurement: process to experimentally obtain one or more quantity values that can reasonably be attributed to a quantity.
Therefore, the process descriptions can be matched to the process names based on these definitions.
References:
ISO 9000:2015 - Quality management systems - Fundamentals and vocabulary
NEW QUESTION # 43
You work for an organisation, 'A', which provides packaged food to the public. You are asked to lead a team (you as the leader and two other auditors) to audit a supplier, 'B', which provides packaging materials to your organisation. It is 4 p.m. and the audit is close to an end; you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting.
The Closing meeting was scheduled
for 5 p.m.
You, as audit team leader, audited top management, the laboratory, and the storage of raw materials.
Auditor 1 audited the two manufacturing lines and dispatch areas.
You to Auditor 1: "What findings would you report?"
Auditor 1: "When reviewing the Dispatch records, I noticed that during the morning two different trucks (Number 011 and 025) delivered the same batch number of the product (Batch 33555). Truck 011 left the plant at 9.15 am and Truck 025 left the plant at
11.30 am. Procedure P-02 Rev.3 says
that trucks should carry a complete batch. The batch number, once on the truck, is captured using a QR device." You: "OK, what do you think?" Auditor 2: "I think that this is a nonconformity." You: "OK. How would you describe the evidence on which the nonconformity will be based"?
Identify which one of the following statements best describes the identified nonconformity.
- A. A product delivered to the client was not identified as required in P-02 Rev 3.
- B. Dispatch personnel are not fully aware of the need to conform to written procedures.
- C. The batch 33555 was delivered split in two different trucks (011 and 025).
- D. Dispatch personnel do not always carry out its activities in conformance with Procedure P-02 rev 3.
Answer: C
Explanation:
According to the definition in ISO 9000, a nonconformity is "non-fulfillment of a requirement". There are three parts to a well-documented nonconformity: the audit evidence to support auditor findings; a record of the requirement against which the nonconformity is detected; and the statement of nonconformity1. In this case, the audit evidence is the dispatch records that show the same batch number of the product being delivered by two different trucks at different times. The requirement is the procedure P-02 Rev.3 that says that trucks should carry a complete batch. The statement of nonconformity is that the batch 33555 was delivered split in two different trucks (011 and 025), which does not conform to the procedure. Therefore, option C best describes the identified nonconformity, as it includes all three parts of a well-documented nonconformity.
Option A is not correct, as it does not state the audit evidence or the requirement. Option B is not correct, as it does not specify the audit evidence or the statement of nonconformity. Option D is not correct, as it does not match the audit evidence or the requirement. References: 1: ISO 9001 Auditing Practices Group Guidance on Nonconformity - Documenting.
NEW QUESTION # 44
You have been nominated audit team leader of a third-party audit. Which of the following could be the two most relevant objectives of this audit?
- A. Evaluate the satisfaction interested parties
- B. Evaluate the benefits obtained since the implementation of the management system
- C. Identify opportunities for improvement
- D. Evaluate the capability of the management system to establish and achieve objectives
- E. Evaluate the effectiveness of the management system
- F. Identify the need of resources
Answer: D,E
NEW QUESTION # 45
......
Get 100% Real Free ISO 9001 ISO-9001-Lead-Auditor Sample Questions: https://www.examtorrent.com/ISO-9001-Lead-Auditor-valid-vce-dumps.html
Accurate ISO-9001-Lead-Auditor Questions with Free and Fast Updates: https://drive.google.com/open?id=1zqwR0n7GzibsnFFbEWPm9LrbLZqs3bIm