Scrum and Kanban are two of the most popular Agile methodologies that are widely used in software development projects. Scrum is a framework for managing and completing complex projects, while Kanban is a visual system for managing work as it moves through a process. The combination of these two methodologies is known as Scrum with Kanban or Scrumban. The Professional Scrum with Kanban level I (PSK-I) Certification Exam is designed for individuals who want to enhance their knowledge and skills in implementing Scrum with Kanban.

 

NEW QUESTION # 44
Which is the most appropriate metric to look at if you want to determine when an item that that has NOT started might be finished?

  • A. Historical Cycle Times.
  • B. Work Item Age.
  • C. Team Capacity.
  • D. Team Velocity.
  • E. There is no such metric.

Answer: A


NEW QUESTION # 45
The Cumulative Flow Diagram is most helpful in visualizing which of the following two metrics? (choose the best two answer)

  • A. Where active items are in the workflow and the typical cycle times for the team.
  • B. Throughput.
  • C. Work in Progress (WIP) trends.
  • D. Cycle Time trends and distributions.

Answer: B,C


NEW QUESTION # 46
Which of the following metrics will likely be reviewed by at the Daily Scrum for a Scrum Team using Kanban? (choose the best two answers)

  • A. Cycle Time.
  • B. Work Age Item.
  • C. Throughput.
  • D. Lead Time.
  • E. Velocity.
  • F. Work in Progress (WIP).

Answer: B,F


NEW QUESTION # 47
True or False: The Scrum Master is responsible for setting the WIP Limits.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 48
Why aren't feedback loop practices included in the Kanban Guide for Scrum Teams? (choose the best answer)

  • A. The Kanban Guide for Scrum Teams builds upon the Scrum Guide. There is no need to explicitly add feedback loop practices as they are already in Scrum.
  • B. Kanban does not require feedback loops as it focuses on improving productivity. Feedback loops only apply when using Scrumban.
  • C. Kanban boards are the only feedback loops needed for Scrum Teams using Kanban.
  • D. A Scrum Team self-manages and decides what feedback loops are necessary to include in their workflow.

Answer: A


NEW QUESTION # 49
Leading indicators: (choose the two best answers)

  • A. about the history of a system.
  • B. tell us about potential future scenarios in a system.
  • C. help us understand and learn from past activities.
  • D. provide us with early warning signs that allow us to correct course.

Answer: B,D


NEW QUESTION # 50
A Kanban board is comprised of which of the following policies? (choose the best two answers)

  • A. Work in Progress (WIP) Limits.
  • B. Class of service policy.
  • C. Each Product Backlog Item type has a separate swim lane.
  • D. Your workflow visualization.

Answer: A,D


NEW QUESTION # 51
What would be the most appropriate reason for a Scrum Team to adjust their Work in Progress (WIP) Limits? (choose the best answer)

  • A. When they want to improve their cycle time, workflow, and focus.
  • B. When the work in progress is lower than the capacity of the Developers.
  • C. When the Developers receive unplanned urgent work during the Sprint.
  • D. When the velocity of the Scrum Team velocity becomes too low.

Answer: A


NEW QUESTION # 52
True or False: The Service Level Expectations (SLE) is an agreement created during the Sprint Planning as a commitment to deliver certain work items by specified dates.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 53
Which analytics chart will help to determine when a specific Product Backlog item, that is currently 'in progress', is projected to be 'finished'? (choose the best answer)

  • A. Control chart.
  • B. Work Item Aging chart.
  • C. Throughput chart.
  • D. Gantt chart.
  • E. Cumulative Flow Diagram (CFD) chart.

Answer: B


NEW QUESTION # 54
An existing Scrum Team wants to apply Kanban practices.
What can the team start doing get begin achieving flow? (choose the best 4 answers)

  • A. Actively managing WIP.
  • B. Inspecting & adapting their workflow.
  • C. Ensuring the product backlog is refined frequently.
  • D. Visualizing their workflow.
  • E. Limiting Work in Progress (WIP).

Answer: A,B,D,E


NEW QUESTION # 55
Little's Law is extremely valuable for directly predicting the future since it gives us a measure of what happened in the past? (Choose the best answer)

  • A. False - Relying only on your Cycle Time measurements may incorrectly influence you to cut your WIP limits.
  • B. True - By understanding our Cycle Time we can use Little's Law to reduce our WIP limits.

Answer: A


NEW QUESTION # 56
True or False: A leading indicator for the length of the feedback loop, for an in progress item, can be its Work Item Age.

  • A. TRUE
  • B. FALSE

Answer: A


NEW QUESTION # 57
In the context of Kanban, which statement best describes flow? (choose the best answer)

  • A. The movement of customer value throughout the product development system.
  • B. The movement of tasks between workflow stages.
  • C. A software development technique.
  • D. An undesirable effect of too much work being present in the system.

Answer: A


NEW QUESTION # 58
True or False: Overall efficiency will automatically increase when you reduce batch size.

  • A. FALSE
  • B. TRUE

Answer: A


NEW QUESTION # 59
True or False: The main role of WIP aging is to help identify flow bottlenecks; where work may be impeded or constrained.

  • A. False
  • B. True

Answer: A


NEW QUESTION # 60
Work in Progress (WIP) is: (choose the best answer)

  • A. The number of work items started but not finished (according to the Scrum Team's definition of "Workflow").
  • B. Equal to the number of PBI's in the Sprint Backlog.
  • C. The number of PBI's that meet the team's definition of "Ready".
  • D. The total of all items in the Product Backlog.

Answer: A


NEW QUESTION # 61
Who is accountable for managing the Kanban board in the Sprint Backlog? (Choose the best answer)

  • A. The Product Owner
  • B. The Developers
  • C. The Scrum Team
  • D. The Scrum Master

Answer: B


NEW QUESTION # 62
Who is accountable for the Definition of Workflow for the Sprint Backlog? (Choose the best answer)

  • A. The Scrum Team.
  • B. The Product Owner.
  • C. The Developers.
  • D. The Scrum Master.

Answer: C


NEW QUESTION # 63
......


Scrum PSK-I (Professional Scrum with Kanban Level I) Certification Exam is a globally recognized certification exam that validates a candidate's understanding and knowledge of the Scrum framework and Kanban. The certification exam is designed for professionals who are involved in product development, project management, and software development. The certification exam is conducted by Scrum.org, a leading global provider of Scrum training and certification.


The Scrum PSK-I Certification Exam is designed to test the knowledge and skills of candidates in applying Kanban practices to their Scrum projects. It assesses the level of understanding of Scrum principles, values, and practices, as well as the ability to implement Kanban practices to optimize the flow of work in the Scrum framework. The exam is based on the Scrum Guide and the Kanban Guide for Scrum Teams, which are the official guides for Scrum and Kanban practices.

 

New PSK-I Dumps - Real Scrum Exam Questions: https://www.examtorrent.com/PSK-I-valid-vce-dumps.html

Dependable PSK-I Exam Dumps to Become Scrum Certified: https://drive.google.com/open?id=1NXBGOoL2wRElm-T06-j5aLcOWYrzy929