In 2026, a question bank is only as good as the team behind it. ExamTorrent pairs 90 verified SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610) practice questions with round-the-clock staff and immediate renewal delivery.
SAP C-TS420-1610 Exam Overview:
| Certification Vendor: | SAP |
|---|---|
| Exam Name: | SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610) |
| Exam Number: | C-TS420-1610 |
| Real Exam Qty: | 80–90 |
| Exam Duration: | 180 minutes |
| Related Certifications: | SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing |
| Exam Format: | Multiple choice questions |
| Passing Score: | 65% (approximately) |
| Available Languages: | English, Chinese (Simplified), Korean, Spanish, Japanese, German |
| Sample Questions: | ![]() |
| Exam Way: | Delivered online via SAP Certification Hub or at authorized testing centres as a multiple-choice exam. |
| Pre Condition: | Basic understanding of production planning and manufacturing processes in SAP S/4HANA recommended. |
| Official Syllabus URL: | https://training.sap.com/certification |
SAP C-TS420-1610 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Demand Management and Material Requirements Planning (MRP) | - Capacity planning fundamentals - Overview of MRP runs and planning strategies - Define and manage demand planning processes |
| Master Data and Setup | - Material master data configuration - Bill of Materials (BOM) and routing basics - Work centers and production resources setup |
| Advanced Planning and Manufacturing Concepts | - Advanced planning in SAP S/4HANA - Integration with supply planning and shop floor control - Process and discrete manufacturing methods |
| Introduction to SAP S/4HANA Production Planning | - Key production and manufacturing concepts in S/4HANA - Overview of SAP S/4HANA PP and supply chain planning |
| Production Execution and Orders | - Lean manufacturing processes - Create and manage production orders - Monitor order progress and confirmations |
What C-TS420-1610 Candidates Ask
The package includes 90 practice questions for the C-TS420-1610 exam, all verified and arranged in a well-balanced mix of difficulty to support progressive study.
- Production Execution and Orders ()
- Advanced Planning and Manufacturing Concepts ()
- Demand Management and Material Requirements Planning (MRP) ()
Let the topic weights guide how you split your study hours.
The SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610) questions are spread across a well-proportioned range of difficulty, from fundamentals to challenging items. That distribution lets you build confidence session by session, and by the time the real test approaches, you have already faced everything it can reasonably throw at you.
Basic understanding of production planning and manufacturing processes in SAP S/4HANA recommended.
The C-TS420-1610 exam contains 80–90 questions within 180 minutes minutes. Rehearsing under the same limit on the ExamTorrent simulator builds calm, practiced pacing.
Our service comes down to three commitments. First, the staff works around the clock online so customer demands about SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610) are met the moment they arise. Second, the team is strictly discreet: customer personal information has never been leaked, and your privacy remains protected. Third, our experts watch the renewal of the question bank, and once a change is found, the updated material goes straight to your mailbox.
SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing (1610) Sample Questions:
Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:
- A. In the plant parameters
- B. In the material master
- C. In the requirements class
- D. In the MRP group
Correct Answer: B,D 🗳️
What capabilities does SAP S/4HANA embedded analytics provide?
There are 2 correct answers to this question.
Response:
- A. Strategic analysis
- B. Real time decision support
- C. Comparison of current data with historical data to identify trends
- D. Automatic update of story boards
Correct Answer: A,B 🗳️
In order to use strategy 70 - Planning At Assembly Level, what order field must be set besides the
planning strategy?
Please choose the correct answer.
Response:
- A. Individual/Collective Indicator
- B. Dependent Requirements indicator
- C. Storage Location MRP Indicator
- D. Mixed MRP indicator
Correct Answer: D 🗳️
Which of the following data objects are updated when a user confirms an operation?
Please choose the correct answer.
Response:
- A. Production order header status
- B. Shop floor information system
- C. Warehouse transfer order status
- D. Production order total order quantity
Correct Answer: B 🗳️
Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:
- A. In the plant parameters
- B. In the material master
- C. In the requirements class
- D. In the MRP group
Correct Answer: B,D 🗳️
Viewing page 1 out of 18 pages.
Viewing questions 1-5 out of 90 questions.